Location:
Odysseus Project, Cosmos Mine, Western Australia.
Time Frame:
August - December 2018.
Client:
Western Areas.
Project Overview:
Merit Lining Systems installed 160,000m2 of 1.5mm HDPE Liner and 160,00m2 of Protection Geotextile in 7 x Water Management Ponds as an erosion protection of the walls.
We have also installed 50,000m2 of Geotextile and 50,000m2 of 1.5mm HDPE Liner in the WDD Pond.
The scope included supply and installation of safety egress netting and depth indicator.
Project required logistics engagement in terms of multiple roster mobilisations, mine site mobilisation rules and keeping wastage of material to minimum.
The project was delivered in the highest quality within the time frame leaving the Client satisfied with our works.